Water Treatment
Installation and restoration of disinfection equipment in north producing area
Country | Hungary |
Year | 2009 |
Contractor / Investors |
Water Works of Budapest MAJOR Sándor |
Engineering services |
Study, Detailed designs |
Technical characteristics |
Hypo and chlorine gas dosing |
Reconstruction of Water Treatment Plant No 1. of Sovata
Country | Romania |
Year | 2008-2009 |
Contractor / Investors |
Alpine SA |
Engineering services |
General and detail designs |
Technological data |
Q = 5.800 m3/d |
Technical characteristics |
Surface water treatment: Intake structure, sand removal, settling basin, sand and marble filter equipment, disinfection, sludge treatment |
Reconstruction of Water Treatment Plant No 2 of Sovata
Country | Romania |
Year | 2008-2009 |
Contractor / Investors |
Alpine SA |
Engineering services |
General and detailed designs |
Technological data |
Q = 3.800 m3/d |
Technical characteristics |
Surface water treatment Settling basin, filter equipment, storage tank, disinfection, sludge treatment |
Békásmegyer Water Treatment Plant (6500 m3 /h) Treatment of gallery water
Country | Hungary |
Year | 2008 |
Contractor / Investors |
Water Works of Budapest MAJOR Sándor |
Engineering services |
Feasibility study |
Technological data |
Q = 150.000 m3/d
|
Technical characteristics |
Treatment of gallery water (Iron and manganese removal) |
Lázbérc Water Treatment Plant Technology development
Country | Hungary |
Year | 2005 – 2007 |
Contractor / Investors |
ÉRV INC (North-Hungarian Regional Water Works) |
Engineering services |
Licensing plan Detailed designs, Licensing documents for commissioning |
Technological data |
Q = 24.000 m3/d |
Technical characteristics |
Surface water treatment Completion of the original technology with ultra filtering and activated carbon filtering Development of chlorination |
Kaposvár Water Treatment Plant – Technology development
Country | Hungary |
Year | 2004 |
Contractor / Investors |
Water Works of Kaposvár |
Engineering services |
Licensing plan Feasibility study |
Technological data |
Q = 20.000 m3/d |
Technical characteristics |
Completion of the original technology with removal of ammonium in 6 independent plants |
Borsodszirák Plant No. I - Capacity increasing and pre-treatment of recharge-water
Country | Hungary |
Year | 2003-2004 |
Contractor / Investors |
ÉRV INC (North-Hungarian Regional Water Works) |
Engineering services |
Detailed designs, Final documentation |
Technological data |
Q = 15.000 m3/d |
Technical characteristics |
Extension of capacity and treatment of surface water for enriching ground water |
Kazincbarcika Plant No. II – Groundwater recharge
Country | Hungary |
Year | 2003-2004 |
Engineering services |
Licensing plan |
Technological data |
Q = 5.000 m3/d |
Technical characteristics |
Surface water intake, water treatment |
Kincsesbánya Water Treatment Plant – Development of the existing technology
Country | Hungary |
Year | 2003 |
Contractor / Investors |
DRV INC (Trans-Danube Regional Water Works) |
Engineering services |
Licensing plan |
Technological data |
Q = 24.000 m3/d |
Technical characteristics |
Reduction of water hardness by partial softening |
Water Treatment Plant Balatonőszöd
Country | Hungary |
Year | 2000 |
Contractor / Investors |
DRV INC (Trans-Danube Regional Water Works) |
Engineering services |
Study General design, Licensing plan |
Technological data |
Q = 10.000 m3/d |
Technical characteristics |
Replacement of the classic process by a membrane filtration technology |