Other Wastewater Treatment Plants - Regional Waste Water Disposal - Sewerage Systems
Sewage project of Town Makó and its region - Reconstruction of pumping stations
Country | Hungary |
Year | 2011 |
Contractor / Investors |
BONEX Építőipari Kft. Budapest Szöllősi Szabolcs |
Technical characteristics |
Building and technology reconstruction of sewage pumping stations: 11pcs (pumps replacement, deodorization, choppers location) |
Szentendre Regional Sewage System - Reconstruction of pump station RSZ I.
Country | Hungary |
Year | 2011 |
Contractor / Investors |
DMRV Zrt. Vác |
Technological data |
5.760 m3/h
|
Technical characteristics |
Installation of storm water pump stations |
WWTP of Révfülöp
Country | Hungary |
Year | 2010-2011 |
Contractor / Investors |
DRV INC. (Trans-Danube Regional Water Works) |
Engineering services |
Feasibility study, permit designs, tender documents |
Technological data |
18.200 PE 2.300 m3/d |
Technical characteristics |
Biological treatment with activated sludge system, nutrients removal, sludge dewatering |
Budaörs Wastewater Treatment Plant
Country | Hungary |
Year | 2010 |
Contractor / Investors |
Törs Kft. OSZOLY Tamás |
Engineering services |
Technology revision |
Technological data |
Biological treatment with activated sludge system 55.000 / 87.100 PE; 6.000 / 9.500 m3/d |
Technical characteristics |
Biological treatment with activated sludge system, nutrients removal, (anoxic and aerobic basins) Mechanical sludge pre-treatment Existing and HIKO technology |
WWTP of Mosonmagyaróvár
Country | Hungary |
Year | 2009-2010 |
Contractor / Investors |
Municipal Water Works |
Engineering services |
Feasibility study, permit designs, tender documents |
Technological data |
98.333 PE 8.500 m3/d |
Technical characteristics |
Biological treatment with activated sludge system, nutrients removal, anaerobic sludge digestion, biogas utilisation |
WWTP of Keszthely
Country | Hungary |
Year | 2009-2011 |
Contractor / Investors |
DRV INC. (Trans-Danube Regional Water Works) |
Engineering services |
Feasibility study, permit designs, tender documents
|
Technological data |
120.890 PE 18.000 m3/d |
Technical characteristics |
Anaerobic sludge digestion; biogas utilisation |
New WWTP of Balatonfüred
Country | Hungary |
Year | 2004-2005 |
Contractor / Investors |
Vegyépszer Co. |
Engineering services |
Detailed design, commissioning |
Technological data |
5.000 m3/d 46.000 PE COD 800-1000 mg/l BOD 450-550 mg/l TSS 280-340 mg/l TKN 80-100 mg/l P 18 mg/l |
Technical characteristics |
Combined stucture: - 800 m3 anoxic tank - 2x1.600 m3 aerobic tanks Final sedimentation tank 2x654 m3 Sludge thickener tank Ø 12 m |
WWTP for three small villages in Hungary
Country | Hungary |
Year | 2003 |
Contractor / Investors |
KÖRTE-Organica |
Engineering services |
General design, detail engineering |
Technological data |
50, 100, 200 m3/h capacity
|
Technical characteristics |
“Living machine process” |
Basic Designs for the Disposal of Waste water and Storm-water in the Downtown of 19 towns
Country | Senegal |
Year | 1999-2001 |
Contractor / Investors |
ONAS On behalf of Scandiaconsult International |
Engineering services |
Preliminary design General design Bidding designs |
Technological data |
Number of inhabitants in the towns: 5.000 – 250.000 inhabitants |
Technical characteristics |
Overall length of the sewerage system: 36 to 590 km. |
Wastewater Disposal and Recycling of the Treated Wastewater in the town of Thiès
Country | Senegal |
Year | 1999 |
Contractor / Investors |
ONAS On behalf of Scandiaconsult International. |
Engineering services |
Preliminary design General design Bidding designs |
Technological data |
Reconstruction and extension of the sewerage system, wastewater treatment plant and recycling of the treated waste water. 210.000 inhabitants |
Technical characteristics |
Phase one: 20 km collector pipe. Waste water treatment plant: Activation process of a small load, with simultaneous stabilisation of the sludge, Clarification of waste water. |